Pembangunan Pipa Transmisi Gas Dumai - Sei Mangkei Segmen 2

Dumai, Riau - Sei Mangkei, Sumatera Utara

BBWS Logo

Ringkasan Progress

Rencana Awal (RA)65%
Realisasi (RI)61.5%
Deviasi-3.5%
Behind Schedule
Target Mingguan3.5%
Sisa Waktu180 hari
Update Terakhir30 Jun 2024

Kurva S - Progress Kumulatif

Perbandingan Rencana Awal (RA) vs Realisasi (RI) mingguan

Data Progress Mingguan

Detail progress kumulatif per periode

PeriodeTanggalRA (%)RI (%)Deviasi (%)Status
W121 Jan 20240.50.3-0.2On Track
W228 Jan 20241.20.9-0.3On Track
W34 Feb 20242.11.8-0.3On Track
W411 Feb 20243.22.9-0.3On Track
W518 Feb 20244.54.2-0.3On Track
W625 Feb 20246.05.8-0.2On Track
W73 Mar 20247.87.5-0.3On Track
W810 Mar 20249.89.4-0.4On Track
W917 Mar 202412.011.5-0.5On Track
W1024 Mar 202414.513.8-0.7On Track
W1131 Mar 202417.216.2-1.0On Track
W127 Apr 202420.118.9-1.2On Track
W1314 Apr 202423.221.8-1.4On Track
W1421 Apr 202426.524.9-1.6On Track
W1528 Apr 202430.028.2-1.8On Track
W165 Mei 202433.731.6-2.1On Track
W1712 Mei 202437.535.1-2.4On Track
W1819 Mei 202441.538.8-2.7On Track
W1926 Mei 202445.642.6-3.0On Track
W202 Jun 202450.046.5-3.5Behind
W219 Jun 202454.250.8-3.4Behind
W2216 Jun 202458.054.2-3.8Behind
W2323 Jun 202461.557.8-3.7Behind
W2430 Jun 202465.061.5-3.5Behind